Te Awa Lakes.
- START DATE: 2022
- CLIENT: Shicks
- LOCATION: Hamilton
JOB TYPE: Stormwater and Wastewater Reticulation
This project involved installing wastewater PVC reticulation in high water table levels and collapsing Hamilton sandy soil. Our expertise and teamwork were the key to success in these challenging conditions. The water was flowing in as fast as we could dig out. Our team was put to the test with controlling the water and keeping us safe. We used trench shields, dewatering systems and a second digger to backfill as we go to prevent pipes moving and/or floating. Planning and preparation were crucial here in completing this project to the highest standards.